Early clearing and leveling of the ground around the Aqua Stadium.
The excavation of the deepest section of the pool has been completed and
fill dirt is being carted in |
|
|
The concrete base of the pool takes shape.
This hopper bottom section is below ground level, with additional walls
being constructed above to create the pools 16 foot depth for the
dolphins and high divers |
| Some of the massive beams are in
place to create the tiered seating around the pool as well as create the
dressing rooms and water treatment facilities |
 |
 |
Heavily reinforced wooden forms have been constructed
to accept the massive weight of the thick concrete walls |
| The walls at their finished height in the shallower
back section of the pool where the dolphins are held during perfomrances |
 |